PROJECT
SCOPE:
To develop a flexible manufacturing line to produce two styles
of tree pruner heads, reducing labor from seven people to three
people while doubling production.
COMPANY:
This company is an international manufacturer of garden equipment
and consumer products.
DESCRIPTION:
System consisted of pallets, which would shuttle from station to
station. Operators would place parts into the pallets with
all riveting and assembly operations done automatically. Changing
pallets and a selector switch from one position to another
accomplishes changeover from one product to another.
UNIQUE
FEATURES:
In order to increase production rates, the pallets had a unique;
cam operated clamping mechanism, which would automatically clamp
upon releasing the pallet.
PROJECT
DURATION:
This project lasted twenty weeks from design to installation.
| Main
pallet transfer line and the three operator workstations
(at red emergency stop switches). |
|
|
Close-up
of the metal prunner head showing the finished product. Note
the spring loaded automatically actuated clamps that are
integral with the pallet.
|
|
|
| This
operator workstation shows the parts for the plastic prunner
head placed into the pallet, ready for release to the riveting
stations. |
|
|
| This
fully automatic station feeds an actuator ball from the white
hopper, down a track and inserts it into the end of the plastic
prunner head, compressing the spring. The head is now ready
for insertion of the blade and retaining screw. |
|
|
| This
view shows three of the four tubular riveters with automatic
bowl fed riveters. |
|